Timelines

Summer of 2016 - Creation of Facilities Task Force

Winter of 2017 - Survey study to gauge community interest and support

Winter of 2018 - Board approves JLG architects with Comstock Engineering as bond partners

Spring of 2018 - Focus group is established to work on bond specifics with architects and engineers

Winter of 2019 - Conceptual plans are shared with staff and community for feedback and adjustments

March 4th - 8th - Survey sent out to public

March 11th - Board approves option A or option B

March 14th - Site visits

May 6th & 7th - Public input meetings at spring concerts

May 11th - Public input meetings at prom

May 20th - MN Legislative Session Ends (Updated status of 7th Street and Regional CTE Dr.)

June 27th - School Board retreat to incorporate legislative updates into facility plan/scope; review project budget and tax impacts

July 15th - School Board meeting to discuss scope/costs and review survey feedback

July 27 - Project information booth at Dilworth Loco Daze

July 29th - School Board meeting for action of project and potential ballot question

August 8th - Project information booth at Glyndon Days

August-October - Submit Review & Comment to MN Department of Education (60 day window)

September-November - Public input and information sessions; open houses and community forums

October-November - Publish Review & Comment

November 5th - Community vote associated with building bond

Winter of 2020 - Approve construction proposals from qualified contractors (dependent on fall voter approval)

Spring of 2020 - Start construction process (dependent on fall voter approval)

Fall of 2021 - Complete construction (dependent on fall voter approval)